Summer Projects Update

College community

Following are updates on several of the summer capital projects under way or upcoming:

Campus-wide sidewalk replacement: Bio-Tech area

The contractor will be removing a section of the sidewalk under the inner campus overhang of the Bio-Tech Building starting TODAY (Tuesday, July 12). The entrance/ exit coming from the nursing area will be closed until July 16. Please follow the signs that will be placed for proper exit from this area.

Roof re-coating

The roof contractor will be continuing the roof re-coating projects in the coming weeks, weather permitting. Parking in the following areas will be affected on these dates:

Friday, July 15 and Saturday, July 16: Orange Hall parking lot will be closed

Monday, July 18 through Saturday, July 23: the Rowley Center and Harriman Hall lot will be closed. The Parking garage will be open for this period for alternate parking.

Friday, July 22 and Saturday, July 23: The Horton Hall Lot will be closed and we discourage parking in front of Bio-Tech, along South Street, on those dates while work is being done on the BT roof.

These dates are subject to change, pending on the weather.

Future updates will be posted as necessary.

Mike Albright
Institutional Advancement
7/12/2016